Vaulted living room of a 1,200 sq. ft. Saratoga ADU looking through to the kitchen

Case Study · Saratoga, California

What goes into building a 1,200 sq. ft. detached ADU in Saratoga?

Monsen Collins Builders took the Faraone ADU from a City of Saratoga building permit in May 2021 to a passed final inspection in March 2022. The 1,200 sq. ft. detached home has two bedrooms, two baths, fire sprinklers, and utilities trenched from the main house, with brick, stucco, and columns matched to the family's existing home.

The Faraone ADU at a glance

Scope
New detached ADU, built ground-up behind the family's existing home in Saratoga
Home
1,200 sq. ft.: two bedrooms, two baths, kitchen, vaulted living and dining room, mudroom with laundry
Site and systems
Tree protection plan through the permit final, fire sprinklers, and gas, water, and electric trenched from the main house
Signature details
Brick porch and stucco columns matched to the main house, tile roof, stain-grade crown and trim, select alder doors
Design
Interior design by Susan Hoffman Interior Design, built by Monsen Collins Builders
Timeline
City of Saratoga building permit May 2021, final inspection passed March 2022

Featured Projects

How we built it

  1. Protect the site first

    Before work began, our crew studied the city-approved tree protection plan, fenced the protected trees, and set storm drain protection. Saratoga's city arborist had to sign off before the building permit could be finaled, so tree protection was part of the job from the first day to the last.

  2. Build the structure and bring the utilities across

    The home sits on a raised, reinforced concrete stemwall foundation over a crawl space finished with a 2-inch rat slab. Gas, water, electric, and low-voltage lines were trenched from the main house, a sewer ejector pump ties the ADU into the house line, and a fire sprinkler system was designed, installed, and inspected.

  3. Match the main house, then finish in wood

    Outside, the brick porch follows the pattern of the main house's porch, the square stucco columns copy its capitals and bases, and the stucco finish matches. Stone panels were traded for stucco and precast details. Inside, trim and baseboards were upgraded to stain grade, with stained crown at the flat ceilings and select alder doors throughout.

Why homeowners trust this process

The homeowners, their interior designer, and our project manager met every week for the length of the build. Each meeting followed a written agenda showing the revised budget, approved change orders, payments to date, the cost to complete, the updated completion date, and the next five working days of work. Every change order was priced and signed by the homeowners, and each progress payment came with a lien release.

Proof

Delivered on Faraone: a 1,200 sq. ft. detached ADU with two bedrooms and two baths; a tree protection plan carried through the permit final, which required the city arborist's sign-off; a fire sprinkler system designed, installed, and inspected; gas, water, electric, and low-voltage lines trenched from the main house, with a sewer ejector pump; a brick porch, stucco columns, and precast window details matched to the main house; and stain-grade trim, stained crown, and select alder doors inside. Permit issued May 2021, final inspection passed March 2022.

Frequently asked questions

How long did it take to build this detached ADU in Saratoga?

The City of Saratoga issued the building permit in May 2021, and the ADU passed its final inspection in March 2022. Every ADU schedule depends on design, permitting, utility work, and site conditions, so we build a schedule for each project and update it at every weekly meeting.

What site work does a detached ADU need?

On Faraone it meant a tree protection plan that the city arborist had to sign off before final, a fire sprinkler system, a sewer ejector pump, and new gas, water, electric, and low-voltage lines trenched from the main house. Requirements vary from lot to lot, which is why we review them early with the homeowner and design team.

Can a new ADU match the look of an existing home?

Yes. The Faraone ADU repeats the main house's brick porch pattern, stucco finish, and column capitals and bases, so the new building reads as part of the original property. Inside, stain-grade trim and select alder doors give it the finish level of a main residence.

How does Monsen Collins Builders keep homeowners informed during an ADU build?

Through a weekly meeting with the homeowners and their designer, run from a written agenda that covers budget, change orders, payments, cost to complete, and schedule. Every change order is priced and signed, and each progress payment comes with a lien release.